Presbyterian Villages of Michigan

Capital Impact Partners provided loans totaling $8.4 million ($8.7 million NMTC allocation) for the renovation and expansion of an approximately 6,000 sq. ft. building into an approximately 23,300 sq. ft. “Program of All-Inclusive Care for the Elderly” (PACE) center.

Investment

  • NMTC Amount: $10,000,000
  • Total Project Cost: $10,678,510

IMPACT

  • 139 FTE jobs
  • 148 construction jobs
  • The Center is expected to serve 250 very low income seniors once the building is complete.
  • 23,300 sq. ft. of real estate

Investor

Project Description

Capital Impact Partners provided loans totaling $8.4 million ($8.7 million NMTC allocation) for the renovation and expansion of an approximately 6,000 sq. ft. building into an approximately 23,300 sq. ft. “Program of All-Inclusive Care for the Elderly” (PACE) center.

MAP

Address: 360 South Merriman Road, Westland, MI 48186

Census Tract: 26163565800

Other Michigan Projects

Tommy Car Wash Systems will expand its manufacturing capacity by constructing a new headquarters and manufacturing facility with $13 million in NMTC allocation.
After sitting idle for more than three decades, the Pere Marquette R.R. Depot became the bustling center of activity that it was over a century ago.
MAC Trailer Enterprises Expands Manufacturing into Mt. Pleasant Facility
This project is for a mixed-use building featuring an indoor farmer's market, mixed-income housing, and retail spaces targeted to independent local businesses.