The project includes equipment and facility upgrades to a paper mill in Quinnesec, MI.

COMMUNITY IMPACT
  • 50 FTE jobs
  • 90 construction jobs
FINANCING SOURCES
  • NMTC amount: $31,017,500
  • Total Project Costs: $50,281,066
  • CDE:
PROJECT LOCATION

West 6705 US Highway 2

Quinnesec, MI 49876

Project Description

The project includes equipment and facility upgrades to a paper mill in Quinnesec, MI. Located in the Upper Peninsula of Michigan, the primary purpose of the project is to increase the renewable electricity generation capabilities of the mill through the installation of a new 28 MW steam turbine generator, upgrades to the existing biomass boiler to allow for increased steam output, purchase and installation of biomass material handling equipment, and construction or installation of related improvements, infrastructure, and equipment.